How we relocate data centers

Do a quick search online and you'll find a variety of ways to relocate or consolidate your IT infrastructure. But there is only one way to do it right.

Quick answer

How does MIGRA relocate a data center?

MIGRA Systems relocates data centers in four phases, scripting move day in 15-minute increments so every task has an owner and a time:

  1. Requirements gathering
  2. Design planning
  3. Implementation planning
  4. Execution

Last updated

At MIGRA, we offer a unique approach to relocating your devices. Using our experience from hundreds of relocation projects, we have designed a way to keep your devices safe and your data secure at every step of the relocation process.

Our proven process, methodology, experience, team members, and our commitment to working with each client as a part of your team and not just a vendor have made MIGRA a leader in our industry.

Our focus is getting your devices relocated safely, securely, and intact. Data center relocations are mission-critical projects. Don't leave this task in the hands of just anyone.

Your focus is keeping your business in motion. Let MIGRA focus on putting your Technology In Motion.

Two technicians seen from behind in a server aisle, one installing a server and one checking a device sheet

Our four phase methodology

Every project follows the same repeatable framework. Each phase builds on the documents produced by the one before it.

  1. Requirements gathering

    We document the Present Method of Operation (PMO): a detailed inventory, Visio drawings, the entire physical network infrastructure, and the logical application linkages for all devices. Our subject matter experts work alongside your core team.

  2. Design planning

    From the PMO we develop recommendations for the Desired Future State (DFS), then the roadmap to get there: net new equipment needs, changes to the telecommunications architecture, and the network within the building.

  3. Implementation planning

    Rack layouts, data center cable plans, a list of tasks to complete before move day, and the Day of Move (DOM) plan with tasks, owners and prerequisites, organized into move groups to reduce downtime and limit risk.

  4. Execution

    Our teams de-install, pack, transport and re-install every device, following the DOM plan line by line and adjusting quickly when the move runs ahead of schedule.

What move day looks like

From validating the inventory of every component slated to move, to identifying software dependencies and mapping all network connectivity, everything is broken down in a detailed day-of-move plan, every 15 minutes, showing each task, whether it's for the client, a vendor, MIGRA or a third party.

  1. Weeks before

    Site walk-throughs

    We cross-check the inventory sheet against the physical location of each device, review the plan with you, map the path for moving devices, and order floor covering to protect the data center floor.

  2. 2 hours early

    Team meeting and walk-through

    MIGRA personnel arrive early. Two-person teams are formed and assigned to areas and racks of the data center.

  3. De-install

    Inventory in, double-checked

    As you release blocks of devices, technicians remove devices, cables, power cords and rails, check the counts, and pack each device with a Device Spec Sheet: server name, serial number, number of cables, cords and rails, and its destination rack and U location.

  4. Transport

    Loaded by priority

    Devices are loaded by destination rack or move group. Critical devices travel first. Every device is tracked by inventory number at de-installation, relocation and re-installation.

  5. Re-install

    Installed, cabled, checked twice

    Installation teams work assigned racks and aisles. A second team double-checks the cabling, then turns the devices over to your team for testing.

Risk assessment at every stage

At every stage of your project, risk assessment and a contingency plan are at the forefront of our process. We know how vital your devices are to your company's success.

Know what's happening at every stage of this mission-critical project with MIGRA on your side. To make sure no vital step is missed, we also break every project into ten steps.

MIGRA services

We have all your data center relocation and migration needs covered.

Questions about our methodology

What are the phases of a data center relocation?

MIGRA runs every data center relocation in four phases: requirements gathering, design planning, implementation planning and execution. Each phase builds on the documents produced by the one before it, from the first inventory to the final device test.

What is a day-of-move plan?

A day-of-move (DOM) plan is the minute-by-minute script for the move itself. MIGRA breaks it down every 15 minutes, listing each task, its owner (the client, a vendor, MIGRA or a third party) and its prerequisites, with devices organized into move groups to reduce downtime and limit risk.

What do PMO and DFS mean in a data center move?

PMO is the Present Method of Operation: a documented picture of how the current data center is built, cabled and connected. DFS is the Desired Future State: how the new environment should look. The move plan is the roadmap from PMO to DFS.

How long does it take to plan a data center relocation?

Planning time depends on the size of the move. In one MIGRA project for a bank, planning began twelve months before the move date, with an eight-month intensive planning process. The last two months were spent scripting and adjusting the day-of-move plan.

See all data center relocation questions · Glossary of relocation terms

Interested in learning more about MIGRA?

Download our white paper for additional insight into successful data center relocations.

Download the white paper (PDF, 365 KB)